Most audit reports fail at the same point. They tell you something is wrong. They do not tell you where it is, how bad it is, or what to do about it — so the report gets filed and nothing changes.

By the Simfy Firesys team· Passive fire protection, Hyderabad
What a Passive Fire Audit Should Document
AuditsA defect list is not an audit. This is what a report needs so you can actually fix things.
The short answer

A passive fire audit report should let someone who was not on the walk find each defect, understand the risk, price the fix and prove it was closed. That means a location that matches your drawings, photographs of both the area and the close-up, the barrier and service type, the recommended action, a severity rating, and space for a closure photograph.

The test of a good report

Here is the only test that matters. Hand the report to someone who was not on the site walk and ask them to find finding number 47. If they can walk to it without calling you, the report works. If they cannot, you have paid for a document that will need the auditor back on site before anything gets fixed.

That sounds obvious. It is also the single most common failure, because a photograph of a hole with a caption reading “unsealed penetration, 4th floor” is useless in a building with two hundred of them.

If a contractor cannot act on the report without the auditor present, the audit is not finished.

Eight things every finding needs

  • Location — building, floor, room or grid reference, and the shaft or riser identifier. It must match the naming your drawings already use.
  • Two photographs — one wide enough to show where you are standing, one close enough to show the defect.
  • Barrier type — what the wall or floor is, and its intended rating.
  • Service passing through — cable bundle, plastic pipe, duct, tray. This decides the fix.
  • The observation — what is actually wrong, in a sentence anyone can read.
  • Recommended action — what should be installed, not just that something should be.
  • Severity — so the list can be spent against in the right order.
  • A closure field — space for the after photograph and a sign-off date.

Eight fields. None of them are difficult. Together they turn a list of problems into a work package.

Severity, so you can spend in the right order

Not every finding is equal, and a flat list forces you to either do all of it or guess. A simple three-level rating removes the guesswork.

LevelWhat it meansTypical timeline
HighAn open route between compartments on an escape route, a stairwell, or between wards. Smoke can travel now.Immediately
MediumA defective or unrated seal in a compartment wall away from escape routes, or a coating breach on protected steel.Next planned window
LowMissing labels, missing records, minor damage that does not currently breach the barrier.Bundle with other works

Scroll sideways on a phone.

In practice, the high-severity list is usually short. That is the useful discovery: most buildings do not need everything redone, they need a specific set of openings fixed and everything else recorded.

Location codes are the boring part that matters

A building has hundreds of near-identical penetrations. Without a naming system that matches your drawings, the report and the building never line up.

The rule is simple: use the codes that already exist. If your drawings call it Block B, Level 4, Riser R3, the report calls it that too. Inventing a new numbering scheme for the audit means someone has to translate twice — once to price the work, once to check it was done.

One line that makes a report usable

Every finding gets a unique reference that carries the location inside it — for example B-L4-R3-012. That single string survives being copied into a snag register, a purchase order and a handover file without anyone losing track of where it is.

Closing the loop

An audit report is only half of the job. The other half is the closure record: the after photograph, the system used to fix it, and a date. Without that, in twelve months you have a report saying the building had forty defects and nothing saying they were fixed.

A workable close-out cycle is five steps: identify, assign, rectify, re-inspect, document. Each finding moves through all five and ends with a photograph in the same file as the one that started it.

This is also the honest test of an auditor. A firm that hands you a defect list and disappears has done the easy half. Our audit page sets out how we run the close-out, including the fact that the audit fee is adjusted if you appoint us for the remedial work — so the list is not a sales document.

Questions to ask before you appoint anyone

  • Can I see a sample report with the location fields filled in?
  • Does every finding carry two photographs and a unique reference?
  • How is severity decided, and by whom?
  • Will the report tell me what to install, or only what is wrong?
  • Is there a closure field, and will you re-inspect?
  • Will the summary reference NBC Part-IV in a form I can hand to an authority?

Six questions. A firm that answers all six easily will produce something your team can use. One that hedges on the sample report is worth walking away from.

Ask for a sample report before you ask for a price. The format tells you more about what you are buying than the number does.
Questions people ask
?
How long should a passive fire audit take?For a typical building, a site walk of one to two days and a report within five working days. Larger or more complex buildings take longer, and that should be stated up front rather than discovered at the end.
?
Should the audit be done by the same firm doing the remedial work?There is no rule against it, but ask how it is kept honest. We state findings with severity and recommended action, and adjust the audit fee against remedial work if appointed — which means the report is not a way of generating a bigger quote.
?
What if the report finds hundreds of defects?That is normal in a building that has never been surveyed, and it is why severity matters. A five-hundred-item list with twelve high-severity findings is a manageable programme; the same list unsorted is paralysing.
?
Can the audit report be used for insurance or accreditation?A properly located and photographed report with an NBC Part-IV summary is the kind of evidence insurers and accreditation bodies ask for. What they will not accept is a general statement of compliance with nothing behind it.

Reading is the cheap part.

If any of this described your building, the next step is someone with a torch and a camera walking your risers.